informed judgement of these experts. The TWG program plans to reevaluate quarterly the scoring of the alternative processes to take into account the relative progress in the R&D efforts for each alternative. A final downselection decision to one process is scheduled for June 2001.

COMMENTS ON CRITERIA

Criterion 1: Schedule Risk. The time frame for completion of the cleanup activity could readily be modified by subsequent funding or policy decisions or by environmental issues. Hence, while the criterion is generally useful in broad terms, it may not be a significant discriminator among the processes. It might be preferable to employ this criteria on a ‘go/no go' basis, in which it would have zero weight unless the calculated risk exceeded the inherent uncertainty.

Criterion 2: Project Cost Reduction Potential. Cost is an important consideration in any project of this magnitude. The costs assigned to the process are likely to be governed largely by the cost of major new facilities, and DOE has carried out extensive cost estimates. These initial estimates did indicate differences between the three processes, but the uncertainty in these estimates is sufficiently large that the projected costs for the three alternatives may be essentially equivalent.3 Cost reduction would result from divergence from the estimates, so if these have been carried out consistently (i.e., with the same level of conservatism), it is unlikely that the criterion will discriminate among the alternatives. At this early stage, cost estimates are not very accurate, and from a policy standpoint there may be a difference between capital costs and operating costs that makes the current estimate of life cycle costs inadequate as a factor for decision making.

Criterion 3: Life-Cycle Costs Through Decontamination and Decommissioning. The federal budgeting procedure takes place on an annual basis and does not ordinarily include life-cycle costs. In addition, funding from more than one DOE Environmental Management office complicates the financial aspects of the cleanup. Consequently, while life-cycle cost is an important issue, the high uncertainties in DOE cost estimates may limit its value in decision making unless the project is privatized.

Criterion 4: Technical Maturity. This criterion appears to provide reasonable input for the downselection procedure, since the major uncertainties identified by the previous committee (National Research Council, 2000) were in areas of science and technology.

Criterion 5: Implementation Confidence. This criterion evaluates the extent to which a given technology has been demonstrated or deployed at large scale, with higher scores assigned when previously used for processing radioactive materials or used within the DOE complex. This does not appear to be independent of Criterion 4, and if given too large a weighting, could result in double counting.

Criterion 6: Minimize Environmental Impacts. Any process selected for implementation would need to gain the necessary regulatory approval, which will be a clear “yes/no” decision. While it is an appropriate goal for each of the alternative processes to minimize radioactive and chemical emissions and generation of secondary waste, the process to be selected will either meet regulatory approval or it will not. The minimization of waste streams is closely tied to project

3  

Kenneth Lang, Department of Energy, oral communication, February 22, 2001.

Suggested Citation:"Comments on Criteria." National Research Council. 2001. Evaluation of Criteria for Selecting a Salt Processing Alternative for High-Level Waste at the Savannah River Site: Interim Report. Washington, DC: The National Academies Press. doi: 10.17226/10088.
×
Page 6
Next: Findings and Recommendations »
Evaluation of Criteria for Selecting a Salt Processing Alternative for High-Level Waste at the Savannah River Site: Interim Report Get This Book
×
 Evaluation of Criteria for Selecting a Salt Processing Alternative for High-Level Waste at the Savannah River Site: Interim Report
MyNAP members save 10% online.
Login or Register to save!

READ FREE ONLINE

  1. ×

    Welcome to OpenBook!

    You're looking at OpenBook, NAP.edu's online reading room since 1999. Based on feedback from you, our users, we've made some improvements that make it easier than ever to read thousands of publications on our website.

    Do you want to take a quick tour of the OpenBook's features?

    No Thanks Take a Tour »
  2. ×

    Show this book's table of contents, where you can jump to any chapter by name.

    « Back Next »
  3. ×

    ...or use these buttons to go back to the previous chapter or skip to the next one.

    « Back Next »
  4. ×

    Jump up to the previous page or down to the next one. Also, you can type in a page number and press Enter to go directly to that page in the book.

    « Back Next »
  5. ×

    Switch between the Original Pages, where you can read the report as it appeared in print, and Text Pages for the web version, where you can highlight and search the text.

    « Back Next »
  6. ×

    To search the entire text of this book, type in your search term here and press Enter.

    « Back Next »
  7. ×

    Share a link to this book page on your preferred social network or via email.

    « Back Next »
  8. ×

    View our suggested citation for this chapter.

    « Back Next »
  9. ×

    Ready to take your reading offline? Click here to buy this book in print or download it as a free PDF, if available.

    « Back Next »
Stay Connected!