| Copyright © 2009. National Academy of Sciences. All rights reserved. Terms of Use and Privacy Statement |
Below are the first 10 and last 10 pages of uncorrected machine-read text (when available) of this chapter, followed by the top 30 algorithmically extracted key phrases from the chapter as a whole.
Intended to provide our own search engines and external engines with highly rich, chapter-representative searchable text on the opening pages of each chapter.
Because it is UNCORRECTED material, please consider the following text as a useful but insufficient proxy for the authoritative book pages.
Do not use for reproduction, copying, pasting, or reading; exclusively for search engines.
OCR for page 26
4
REACHING AGREEMENT WITH THE
OFFICE OF MANAGEMENT AND BUDGET
In which GSA and OMB reach agreement to proceed but
a seed is sown that will come back to haunt the project.
EARLIER GSA AND OMB RELATIONSHIPS
The problems between GSA telecommunications and OMB predated the
FTS2000 project and went back at least to the end of Telpak in 1981.
At the time of Telpak's demise, GSA had gone to OMB acting as a
spokesman for its customer agencies to seek a supplementary
appropriation for the almost $100 million shortfall due to AT&T's
tariff raises. OMB did not accede to that request, placing the
shortfalls on the shoulders of the agencies, effectively causing them
to question FTS cost and service. Deregulation had advanced enough
that the climate was right for OMB to question GSA's role in providing
telecommunications centrally to the government.
OMB also questioned GSA's control over the fund used to operate the
FTS. The Federal Telecommunications Fund was a revolving fund used to
pay all costs associated with the system and it was reimbursed on a
prorated usage basis by the customer agencies. Inevitably in time of
centralization and monopoly, such funds can be loosely managed.
OMB pressured GSA to undertake long-range telecommunications
planning as early as 1981. For various reasons this was not
accomplished until 1984 and annual pressure on GSA by OMB to reveal its
plans brought little by way of answers or tangible results.
Adding to this fertile ground for discord was the fact that the
powers of the two agencies overlap. This conflict and overlap had been
exacerbated in the area of information resources by passage of the
Paperwork Reduction Act in 1980, which increased OMB's role in managing
information technology.
Also, as previously mentioned, the largest and most powerful
customer agencies of the FTS, dissatisfied with GSA, had begun to
petition OMB for permission to leave the FTS and go their own way.
This situation had become acute with the major cost increase due to
Telpak's termination.
All of these interplaying forces set the stage for a rocky
relationship between GSA and OMB in the early 1980s in the area of
telecommunications policy and management.
26
l
OCR for page 27
27
Things first came to a head at GSA's budget hearings with OMB in
the fall of 1983. The OMB team was well organized and well prepared to
question the telecommunications program. GSA was not well prepared to
defend itself. This event was quickly followed in December 1983 with a
letter from OMB to GSA indicating that the FY 1986 budget cycle would
mark deregulation of FTS--in ether words, terminate FTS and get out of
the business (Note 1~.
It seems in retrospect that these disagreements were mainly
contained to the permanent civil service level rather than initiated by
the political appointees. The disagreement took on the characteristics
of a civil service feud and, while GSA was leaderless from when Carmen
left in February 1984 to June 1985 when Golden arrived, OMB staff took
advantage of this vacuum (Note 2~. The December letter was to be only
one of many from OMB, though all were signed by highly placed political
appointees ready to let their staff handle the FTS in the intervening
time before GSA gained a new administrator (Note 3~.
GSA held many meetings with OMB to explain the complexities
associated with shutting down the old FTS. However, no one at OMB
seemed to appreciate the issue or to guide the staff, which had little,
if any, background in telecommunications and management at that time.
OMB pressed steadily onward, against the greater efforts and wishes of
GSA, to issue in April 1984 a deregulation bulletin in the Federal
Register. In response to this, GSA wrote directly to Stockman in May
1984 indicating that this action caused much apprehension and GSA had
serious reservations that this would best serve the government or was
appropriate (Note 4), but to no avail.
This was the foundation of OMB/GSA relations on which the FTS2000
project was to be built.
KALBA BOWEN, THE PANEL, AND GAINING OMB SUPPORT
In retrospect, Kalba Bowen's project team, while being
knowledgeable in telecommunications policy, were not experienced in the
nature of large private networks. This made GSA's task in explaining
their strategy very difficult.
The blue-ribbon panel, on the other hand, was constituted of
members with strong credentials in managing and running large networks
for government and for private sector corporations. It included
members from Westinghouse and General Electric, corporations that run
two of the private networks nearest in size to the FTS. The panel also
included the ex-head of telecommunications at the Department of State,
and the retired head of the Defense Communications Agency (DCA) (who
after his retirement was CEO of American Satellite and also sat on
several National Research Council committees). Another member was the
retired head of development of networks for AT&T, and no doubt the most
knowledgeable person about state-of-the-art technology. The panel was
rounded out with members from academe, one of whom acted as the
chairman (Note 6~.
OCR for page 28
28
In many ways, during the intervening time of preparing the panel
and the Kalba Bowan contract, Golden reached a high level of comfort
with the FTS2000 approach. Consequently, while both served as an
important mechanism for the checking, exploration, and debate that
brought him to 100 percent confidence, their biggest contribution was
probably their role in helping GSA reach agreement with OMB. Golden
was a member of the Reagan administration's establishment and so he had
access to, and the confidence of, decision makers at OMB. The process
he described of independently evaluating FTS2000 for himself before
reaching a conclusion satisfied the OMB management and provided a
procedure for all parties to reach agreement, including a participatory
mechanism for the OMB permanent staff.
The panel was given access to all documentation concerning the
FTS2000 project for their detailed analysis. It then first met for a
two-day session on February 13 and 14, 1986. The first session was to
hear from a variety of sources as to FTS replacement issues and
alternative approaches. Golden attended the panel deliberations
throughout their proceedings. There were several formal presentations:
the stage was set with the history of the FTS, then the panel heard
from Howard Anderson of the Yankee Group who in general terms endorsed
the approach (particularly fully integrated services). BellCore
discussed ISDN and endorsed FTS2000's integration of services. A
speaker from the Gartner Group outlined various AT&T alternative
approaches, such as the AT&T intelligent network and an Electronics
Tandem Network based system. There were other speakers: General
Motors/Electronic Data Systems (GM/EDS) described its approach to
network replacement and ETI also made a presentation of unfolding
public policy. The final presentation covered the GSA approach. Key
steering committee members from Treasury, the Veterans Administration,
and the Department of Energy attended in support of the project and to
advise from the users' perspective. Golden invited OMB and it sent
representatives from each of its three divisions: budget, regulatory
affairs, and government-wide management.
Meanwhile, Kalba Bowen began interviewing the FTS2000 team in
January 1986, and the GSA team led them through the logic of the
FTS2000 approach. In lengthy discussions, questions were answered and
misconceptions were eliminated, leading to findings that began to
parallel GSA's own. However, a bombshell was dropped in the draft
final report at the end of April. Kalba Bowen presented four major
conclusions. They had concluded (as had GSA) that the system should
not be decentralized with each agency going its own way. Secondly,
they rejected any approach that reduced the menu of services from the
full menu of FTS2000 (endorsing GSA's move from only voice to
integrated services). They also endorsed the FTS2000 general approach
on a cost basis. But in a fourth recommendation, which was a surprise
to GSA, they indicated that the best choice would be to take the
FTS2000 approach but to make two awards to two independent vendors.
The GSA team could not understand the origin of the recommendation
or see how to implement it. Questions immediately were raised: How
did two awards make better sense than one award when there were only
OCR for page 29
29
three companies who had declared that they would definitely bid on
FTS2000? Wouldn't this make the Government more captive to the
vendors? How could GSA break up the requirements into two bid
packages? When GSA ended up with two networks, how would they manage
interconnection, both normally and in times of emergency? And, the
most severe problem, how would they transition two systems with the
attendant risk of adding complexity to an already risky transition?
These questions were disturbing in themselves, but more so as Kalba
Bowen was not able to address them and could not describe the basis for
their recommendation.
As a supplement to their draft report delivered on April 22, and in
response to GSA concerns with the recommendation to make multiple
awards, Kalba Bowen provided a detailed rationale for their decision in
a May 30 memo to GSA (Note 7) at the time of delivering their final
report. This memo indicated that the issue of competition was
paramount in obtaining good service prices. They further indicated
that in their opinion AT&T would enjoy an overwhelming competitive
advantage over other potential bidders and that the procurement would
thus not yield the low bids GSA expected. They also discounted the
competitive pressure of agencies being voluntary participants in
FTS2000 and thus being able to continuously seek better prices
elsewhere. Hence, they said, there would be little pressure to
maintain low rates throughout the contract life. In conclusion, they
said that the multi-vendor strategy would ensure considerably more
competitive bidding and increased competitive pressures on the winning
vendors following contractor award. They admitted that the change
would result in slowing the procurement and introducing new
complexities which could reduce the efficiency of the procurement and
the system transition. The effect of these complications and delays
could be to reduce the overall benefit which the government would
achieve from the FTS replacement.
On August 17, the blue-ribbon panel met for their final session to
listen to the Kalba Bowen findings and recommendations, to deliberate,
then to advise the administrator on the proper course of action. Their
reaction to Kalba Bowen was very much the same as GSA's: What is the
advantage of doing this? How can it be implemented? The answers were
not forthcoming. The panel retired to deliberate, then met with Golden
and was unanimous in advising Golden that GSA proceed with FTS2000 as
structured and that GSA should not consider breaking up the procurement
into two awards.
With the panel's recommendation and Golden's acceptance of it,
GSA's relationship with OMB became positive, with each side
communicating concerns and answers in a spirit of trying to reach
agreement and get the REP issued as soon as possible. OMB's remaining
concerns were serious ones and ones that GSA also had deeply ~
considered.
The first of OMB's concerns was how GSA would manage FTS2000 once
it was awarded. In correspondence with OMB, GSA formally proposed a
solution that had been worked out with OMB staff in previous weeks.
GSA would develop a tripartite management team consisting of: (1)
OCR for page 30
30
GSA's own management and technical resources; (2) a federally funded
research and development center consisting of multidisciplined experts
in management and telecommunications to support GSA's management; and
(3) reliance on a technical assistance and management services (TAMS)
contractor for technical support.
The second item that concerned OMB was the most difficult and
serious. It became the heart of all remaining conflict in the
program: How does the government avoid being locked-in to a single
contractor and ensure ongoing competition within the program? This
question had been recognized at the very beginning of the project as a
pivotal issue.
GSA's approach to ensure ongoing competition was rooted in a belief
that agencies would make rational decisions about consuming FTS2000
services and that a free market would bring sensible actions on their
part. It was also one that recognized the transition from the old
network was a uniquely difficult problem, one that was complex enough
to be considered paramount. Consequently, GSA's tack was to:
1. Award the contract to a single prime contractor. This would
not only ensure the lowest possible initial prices but would make the
program more manageable, particularly during the difficult transition,
but also throughout the life of the contract;
2. Offer only a minimum guarantee to the successful contractor,
namely, the traffic expected to be consumed during the transition
period. Any revenues after that would have to be earned by the prime
contractor keeping the customers satisfied and providing low-cost and
high-quality service. This was possible because the industry had
excess capacity and was highly competitive; and
3. Make participation in the FTS2000 service entirely voluntary so
that customers could walk away from the service if they were not
satisfied. This was feasible because there would no longer be a
dedicated system. Voluntary participation would ensure competition
from outside FTS2000 (Note 8~.
The focus of GSA's strategy for ensuring ongoing competition rested
on these points. Experience with the old FTS had shown that a
locked-in vendor was definitely harmful to the customers and did not
ensure low-cost, high-quality service. However, GSA had observed that,
even in the case of the old mandatory FTS, when user agencies suffered
enough from high-cost and low-quality services they were prepared to
take the drastic actions needed to remove themselves from the system.
GSA felt that if this was true under the inflexible environment of a
mandatory hardware system, it would be even easier under the proposed
services contract. Agencies leaving the FTS2000 service would present
minimal transition problems and minimum impact on remaining agencies.
This was an important part of the strategy that was later to be changed
by Congress.
OMB was satisfied with GSA's approach to its concerns and, with
minor modifications, accord was formally reached in a series of letters
culminating in Golden's final notice to OMB that all issues were
settled (Notes 9 and 10~.