Chronology of the Siting of the Sulphur Mountain NEXRAD
Date |
Event |
August 1984-December 1984 |
SRI International, Inc. receives input on site suggestions from the Federal Aviation Administration Western Pacific Region, the National Weather Service Western Region, and the NEXRAD Joint System Program Office |
March 1985 |
Analysis of the local atmospheric inversion statistics are provided to SRI International, Inc. |
March-July 1985 |
SRI International, Inc. visits many sites in the Los Angeles area |
April 1986 |
SRI International, Inc. completes the Preliminary Site Survey for the Los Angeles, California area (Sulphur Mountain site) |
August 1987 |
SRI International, Inc. completes the In-Depth Site Survey for the Los Angeles, California area (Sulphur Mountain site) |
1987 |
Sulphur Mountain selected as the best of 32 candidate locations |
1992 |
SRI International, Inc. reviews alternative siting criteria |
November 15, 1993 |
Construction of Sulphur Mountain NEXRAD begins |
December 16, 1993 |
Sulphur Mountain NEXRAD installation complete |
January 1994-March 1994 |
Sulphur Mountain NEXRAD tested |
March 1994 |
Sulphur Mountain NEXRAD accepted |
December 1994 |
Sulphur Mountain NEXRAD commissioned |