The United States is in the process of destroying its chemical weapons stockpile. In 1996, Congress mandated that the weapons at two sites, Blue Grass Army Depot in Kentucky and Pueblo Chemical Depot in Colorado, would not be destroyed by incineration and that the Department of Defense should demonstrate and select alternative methods. In 1999, Congress also passed Public Law 105-261, which required that the Under Secretary of Defense certify “in writing to Congress” that the alternative technology would “be as safe and cost effective for disposing of assembled chemical munitions as is incineration of such munitions….”
The Assembled Chemical Weapons Alternatives (ACWA) program was established in response to these mandates. Because the selected alternatives at each site would be new applications of existing technologies, the Army designated the facilities used to implement the alternatives as pilot plants—the Blue Grass Chemical Agent Destruction Pilot Plant (BGCAPP) and the Pueblo Chemical Agent Destruction Pilot Plant (PCAPP).
The Program Manager for Assembled Chemical Weapons Alternatives is overseeing the efforts of systems contractors to develop and test equipment to be used in the designs for constructing the two disposal pilot plants. Among the first-of-a-kind equipment under development for the BGCAPP are two metal parts treaters (MPTs), which would be used primarily for the treatment of washed-out metal munitions cases from which the agent has been drained. The MPTs could also be used to treat secondary waste generated during the destruction operations and waste materials generated during facility closure operations. During recent testing, results have shown the heat-up times of trays of munition casings to be longer than expected. Another issue that has developed involves problems in sealing the MPT as the temperature inside is increased. The Program Manager for Assembled Chemical Weapons Alternatives requested that the National Research Council (NRC) form a committee to review ongoing testing to investigate and determine causes for the longer-than-expected heat-up times and other issues concerning the MPT design. The full statement of task for the Committee to Review and Assess Developmental Issues Concerning the Metal Parts Treater Design for the Blue Grass Chemical Agent Destruction Pilot Plant is given in the Preface.
Contracts to design, build, operate, and close both pilot plants were awarded to Bechtel International, teamed with Parsons Engineering. For PCAPP, Parsons is a subcontractor to Bechtel. For BGCAPP, Bechtel and Parsons formed a joint venture called the Bechtel Parsons Blue Grass Team (BPBGT) and are teamed as prime contractors. These contractors tailored the specific design of the respective facilities to the content of each site’s stockpile.1
Originally the MPT was planned for use at both BGCAPP and PCAPP to decontaminate metal parts. The current PCAPP design now calls for a munitions treatment unit (MTU) to decontaminate projectile and mortar casings. The MPT uses radiant and convection heating in an enclosed metal cylinder to raise metal parts to 1000ºF for a duration of 15 minutes in order to decontaminate these materials. Steam is used as a carrier or sweep gas to remove vapors and particulates released during heating. The intention is also to use the MPT to treat contaminated secondary waste before its off-site disposal.
The two MPTs being developed for the BGCAPP are
Below are the first 10 and last 10 pages of uncorrected machine-read text (when available) of this chapter, followed by the top 30 algorithmically extracted key phrases from the chapter as a whole.
Intended to provide our own search engines and external engines with highly rich, chapter-representative searchable text on the opening pages of each chapter.
Because it is UNCORRECTED material, please consider the following text as a useful but insufficient proxy for the authoritative book pages.
Do not use for reproduction, copying, pasting, or reading; exclusively for search engines.
OCR for page 1
summary
The United States is in the process of destroying its concerning the MPT design. The full statement of task for
chemical weapons stockpile. In 1996, Congress mandated the Committee to Review and Assess Developmental Issues
that the weapons at two sites, Blue Grass Army Depot in Concerning the Metal Parts Treater Design for the Blue
Kentucky and Pueblo Chemical Depot in Colorado, would Grass Chemical Agent Destruction Pilot Plant is given in
not be destroyed by incineration and that the Department of the Preface.
Defense should demonstrate and select alternative methods. Contracts to design, build, operate, and close both pilot
In 1999, Congress also passed Public Law 105-261, which plants were awarded to Bechtel International, teamed with
required that the Under Secretary of Defense certify “in writ- Parsons Engineering. For PCAPP, Parsons is a subcontrac-
ing to Congress” that the alternative technology would “be as tor to Bechtel. For BGCAPP, Bechtel and Parsons formed
safe and cost effective for disposing of assembled chemical a joint venture called the Bechtel Parsons Blue Grass Team
munitions as is incineration of such munitions. . . .” (BPBGT) and are teamed as prime contractors. These con-
The Assembled Chemical Weapons Alternatives tractors tailored the specific design of the respective facilities
to the content of each site’s stockpile.1
(ACWA) program was established in response to these man-
dates. Because the selected alternatives at each site would
be new applications of existing technologies, the Army
The meTal ParTs TreaTer aNd The
designated the facilities used to implement the alternatives
mUNiTioNs TreaTmeNT UNiT
as pilot plantsthe Blue Grass Chemical Agent Destruc-
tion Pilot Plant (BGCAPP) and the Pueblo Chemical Agent Originally the MPT was planned for use at both
Destruction Pilot Plant (PCAPP). BGCAPP and PCAPP to decontaminate metal parts. The
The Program Manager for Assembled Chemical Weap- current PCAPP design now calls for a munitions treatment
ons Alternatives is overseeing the efforts of systems con- unit (MTU) to decontaminate projectile and mortar casings.
tractors to develop and test equipment to be used in the The MPT uses radiant and convection heating in an enclosed
designs for constructing the two disposal pilot plants. Among metal cylinder to raise metal parts to 1000°F for a duration
the first-of-a-kind equipment under development for the of 15 minutes in order to decontaminate these materials.
BGCAPP are two metal parts treaters (MPTs), which would Steam is used as a carrier or sweep gas to remove vapors and
be used primarily for the treatment of washed-out metal particulates released during heating. The intention is also to
munitions cases from which the agent has been drained. The use the MPT to treat contaminated secondary waste before
MPTs could also be used to treat secondary waste gener- its off-site disposal.
ated during the destruction operations and waste materials The two MPTs being developed for the BGCAPP are
generated during facility closure operations. During recent
testing, results have shown the heat-up times of trays of mu- 1The stockpile at the Blue Grass Army Depot includes two nerve agents
nition casings to be longer than expected. Another issue that and a blister agent in various types of munitions. The agents are nerve agent
has developed involves problems in sealing the MPT as the sarin (GB) (C4H10FO2P), nerve agent VX (C11H26NO2PS), and Levinstein
mustard agent (H) (C4H8Cl2S). The nerve agents are in M55 rockets and 8-
temperature inside is increased. The Program Manager for
inch or 155-mm projectiles. The mustard agent H is in 155-mm projectiles.
Assembled Chemical Weapons Alternatives requested that
The stockpile at the Pueblo Chemical Depot consists of 105-mm boxed
the National Research Council (NRC) form a committee to cartridges, palletized 155-mm projectiles, and 4.2-inch mortars, all of which
review ongoing testing to investigate and determine causes are filled with one of two forms of mustard agent: distilled mustard agent
for the longer-than-expected heat-up times and other issues (HD) or mustard agent HT.
OCR for page 1
ReView aNd aSSeSSMeNT OF deVelOPMeNTal iSSueS CONCeRNiNg The MeTal PaRTS TReaTeR deSigN
designated as first-of-a-kind equipment because they are to gather data for further effort with the CFD model.
• erform test runs and cycles of components to make ob-
P
unique, are being designed for this particular application, and
servations of critical design parameters that apply to the
have never been used in an actual process. A small-scale test
FOAK unit under design—particularly those that affect
unit called the Technical Risk Reduction Program (TRRP)
the risk of scale-up to the full-scale unit. These include,
MPT was fabricated to demonstrate the operation of the MPT
but are not limited to projectile paint debris generation and
concept for the decontamination of metal parts and waste. In
accumulation, thermal expansion stresses and deformation
this report, the phrase “first-of-a-kind” or “full-scale MPT” points, interferences, Gaussian field measurements and lo-
is used to describe the full-scale equipment, and the term calized heating effects, and wall temperature distribution.
“TRRP MPT” is used to describe the three-quarter-scale
version. The TRRP MPT testing used an off-gas treatment sys-
The PCAPP design calls for an MTU to decontaminate tem that included a catalytic oxidizer unit rather than a bulk
the projectile and mortar casings. The MTU, an adaptation oxidizer unit (more accurately called a flameless thermal
of a metal annealing oven, is a continuous-belt muffle-type oxidizer) and did not include the venturi scrubber. Thus, the
oven with material-handling equipment at the feed and flow of off-gas from the MPT enclosures was demonstrated,
discharge ends. Modifications include new feed and exit but not the off-gas treatment system configuration or equip-
sections and a muffle large enough in cross section (10 in. ment that will be provided for the full-scale MPT. The off-gas
high by 30 in. wide) to accommodate 155-mm projectile treatment system bulk oxidizer unit is also considered to be
bodies riding on the metal conveyor. The muffle section is a first-of-a-kind system.
also long enough to ensure that all parts of the munitions TRRP MPT testing was performed using surrogates of
reach 1000oF for at least 15 minutes at the operating speed all munitions metal parts and waste feed streams anticipated
of the metal conveyor. for the two BGCAPP full-scale MPTs. All feed streams were
The committee was not charged with evaluating the tested. However, the BPBGT terminated the waste stream
MTU in detail. What this report presents is a technical testing before the completion of all planned tests because
description and evaluation of the MPT (Chapters 2-4) plus it was believed that sufficient data to design the full-scale
an evaluation of the technical feasibility of replacing the MPT had been obtained. All feed streams were tested to the
MPT with an MTU and supplemental decontamination units extent allowed by existing permits at the Parsons fabrication
and autoclaves such as those being designed and tested for facility. The permitting limitation prevented testing of the
PCAPP (Chapter 5). energetics batch hydrolyzer waste with energetics remnants
and halogenated materials.
During testing, the TRRP MPT unit experienced re-
assessmeNT oF meTal ParTs TreaTer TesTiNG
curring operating problems, such as mechanical failures
acTiViTies
and munitions bodies taking longer than expected to reach
The MPT concept has been subjected to testing in the necessary high temperatures as estimated by computer
TRRPs, with most of the pertinent testing conducted under modeling.
the Bechtel TRRP 05c test plan (BPBGT, 2007d). This test- The committee grouped the MPT test results into three
ing has used the three-quarter-scale TRRP MPT. areas for review and evaluation: (1) mechanical issues and
The testing objectives as given in the TRRP 05c test plan (2) secondary and closure waste treatment issues, which are
were as follows (BPBGT, 2007d): assessed in this section, and (3) results of thermal testing,
modeling, and predicted throughput of the MPT, which are
• emonstrate reliable mechanical performance of all parts
D assessed further below.
and functions of the MPT design, including seals, doors,
bearings, and projectile jamming.
• emonstrate BGCAPP-specific design improvements mechanical issues
D
such as: projectile orientation, steam-injection orientation,
gas take-off orientation, and tray design to improve heat- New Door Closure Mechanism and Seals
up.
Difficulties with getting an acceptably tight closure on
• alibrate the computational fluid dynamics (CFD) model
C
the air lock and main chamber doors for the TRRP MPT
of the test unit on VX 155-mm projectiles to serve as a
basis for first-of-a-kind (FOAK) full-scale unit modeling. have resulted in a change in the design of the door closure
Inherent in this objective is the necessary demonstration mechanism and seals for the full-scale MPT. Instead of the
that the MPT can heat all parts of materials fed to it to J-type sliding closure mechanism used on the TRRP MPT,
1000oF for at least 15 minutes at a rate that meets expected the door for the full-scale MPT will be moved against the
feed rates during operation.
closure face by using a two-direction cam design recom-
• emonstrate treatment of simulated energetics batch hy-
D
mended by a commercial oven contractor. In addition, the
drolyzer (EBH) rocket warhead debris.
seal material design has been altered to give the equivalent
• emonstrate limited secondary-waste treatment options
D
of two gaskets between the door and closure face.
OCR for page 1
SuMMaRY
Bearings for the Conveyor Rollers or (2) if the waste has been subjected to thermal treatment at
1000°F for 15 minutes. The second criterion, formerly called
The Graphalloy® bearings for the conveyor rollers in the
treatment to 5X, was a requirement for off-site shipment until
main chamber experienced galling and other wear failures
June 2004 when the criteria on WCL were introduced. The
attributed to oxidation/corrosion at the main chamber operat-
BPBGT plans to heat all secondary waste to 1000°F for at
ing temperature. Three different bearing materials were eval-
least 15 minutes in the MPT. At that temperature, in the very
uated: “improved” Graphalloy®, Stellite, and Deva (Deva-
low oxygen activity environment of the MPT, many second-
Mogul sintered metal). All materials experienced wear, and
ary waste materials will pyrolyze, leading to the formation
the BPBGT concluded that the “improved” Graphalloy®
of chars and tars. By lowering the temperature to ~500o F for
bearings were acceptable, although they exhibited some
1 to 2 hours, six nines (99.9999 percent) agent destruction
pitting. During full-scale MPT testing, the BPBGT intends
and removal efficiency should be achievable, and char and
to reconsider Stellite bearings that are interchangeable with
tar formation should be greatly reduced.
the Graphalloy® bearings. The BPBGT has also developed
maintenance protocols that shorten replacement times for
resUlTs oF Thermal TesTiNG, modeliNG, aNd
bearings as much as possible.
PredicTed meTal ParTs TreaTer ThroUGhPUT
Heating Zones TRRP testing of secondary waste treatment in the MPT
was conducted at the Parsons fabrication facility in Kenne-
The full-scale MPT will use two heating zones in the
wick, Washington, in May 2007. The test results were gen-
main chamber. Each will be capable of about 450 kW of in-
erally favorable. However, the range of waste types treated
duction heating. The TRRP MPT used one 600-kW induction
was narrow, and the total amount of waste treated was small.
heater. The use of two-zone heating in the full-scale MPT
Thus, the committee recommends that the BPBGT perform
main chamber should improve heating rates and control of
more comprehensive testing during systemization, using
heating. It is unclear whether maintenance on one MPT will
waste representative of that encountered during closure as
be possible while the other is in operation. If not, the avail-
well as various types of secondary waste from operations and
ability of the MPTs would be reduced, since both would
maintenance. Heat-up times for projectiles located in the trays
have to be shut down if either required in-room maintenance.
passing through the TRRP MPT were measured and predicted
TRRP testing and CFD modeling showed that certain areas
to demonstrate that the metal parts at all locations in the tray
of some projectiles were heating more slowly than the rest
could be heated to 1000°F for at least 15 minutes within a
of the projectiles. This slower heating required longer heat-
total time duration that supported the design production rate.
up times to achieve a uniform 1000°F for 15 minutes for
The experimental data and the modeling focused on the tem-
all projectiles. After its review of the chamber design, the
perature-time profiles for projectiles at specified locations in
BPBGT concluded that the slow heating resulted from “shad-
the tray. The key elements of this effort were as follows:
owing” of parts of the projectiles during the radiant heating
process. The shadowing is being addressed by redesign of
• hermocouple measurements of the surface tempera-
T
the projectile trays, the superheated steam inlet header, and
ture were made on a limited number of projectiles at
the off-gas outlet header.
specific locations in the tray as they passed through
the MPT and were heated.
• redictions of the temperature distribution in the pro-
secondary and closure Waste Treatment issues P
jectiles were made by using a CFD thermal modeling
Waste to be treated in the MPT includes the washed
program that was compared with a previous model
munitions bodies from the munitions washout system, solid
used in initial PCAPP MPT testing. However, all
residues from the energetics batch hydrolyzer, and secondary
model results must be validated with experimental
and closure waste. Agent-contaminated waste will be treated
data, as discussed elsewhere in this report.
by chemical decontamination. When chemical decontamina-
tion cannot be used, waste (e.g., agent-contaminated pallets)
Experimental Temperature Measurements
will be treated in the MPT before off-site disposal. Secondary
waste that is not agent-contaminated is not expected to be
Type K thermocouples encased in stainless steel sheaths
processed through the MPT.
were mounted to the top and bottom of three projectile cas-
In general, secondary waste can be shipped off-site
safely if it meets one of two criteria: (1) if analysis shows
by EPA’S toxicity characteristic leachate procedure (TCLP) applied to the
levels less than the applicable waste control limits (WCLs)2
residuals from the metal parts treater. The WCL may also, or additionally,
be based on agent concentration in the air space above the containerized
2WCLs and the analytical methods required to demonstrate that they waste treatment residuals. Minimum required levels are typically 1 STEL
(short-term exposure limit )—0.0001 mg/m3 for GB, 0.00001 mg/m3 for
have been achieved vary by state. In general, the WCL is defined as 20
VX, and 0.003 mg/m3 for HD.
parts per billion (ppb) for GB and VX and 200 ppb for HD, as determined
OCR for page 1
ReView aNd aSSeSSMeNT OF deVelOPMeNTal iSSueS CONCeRNiNg The MeTal PaRTS TReaTeR deSigN
• ffective thermal treatment of secondary waste with-
ings in order to allow the monitoring of temperature-time E
profiles in the prototype TRRP MPT. Selection of the loca- out excessive fouling of the duct work leading to the
tions on the casings was aided by use of the CFD thermal bulk oxidizer;
• uccessful integration of the MPT with its flameless
model to identify potential cool spots. S
thermal oxidizer (i.e., the bulk oxidizer) and cyclone;
and
Temperature Prediction by Computational Fluid Dynamics
• omplete destruction of energetic materials in the
C
Thermal Modeling
waste stream of the energetics batch hydrolyzer
The BPBGT used a mathematical model for comparison without adversely affecting the MPT.
with the TRRP experimental measurements and to predict
Finding. The current range of heat-up times of munitions in
the performance of the full-scale MPT for BGCAPP. The
BPBGT model gives spatial and temporal temperature the MPT should not affect the overall schedule of BGCAPP
behavior of the parts being processed in the MPT. The pur- operations.
pose of the modeling was to show that the MPT design was
• eat-up times in the TRRP tests are close to target
adequate for treating munitions at 1000°F for 15 minutes H
while meeting operational and schedule requirements and and appear to be capable of being improved by rais-
that the design could guide the scale-up and the testing of ing the wall temperature of the full-scale MPT.
• FD modeling predicts correct trends in temperature-
the full-size unit. Comparison with the experimental mea- C
surements was used to validate and modify the model. The time profiles and locations of cold spots and should
improved model appears to be fairly rigorous. The code is be useful in guiding the design and testing of the
based on a nonlinear solver that (1) is accurate to second full-scale MPT.
• he processing rate of projectile bodies in the MPT is
order in space and time; (2) globally and locally conserves T
mass, momentum, and energy; and (3) allows a choice of not on the critical path of the process throughput. The
finite-element shape function. The model handles multimode design calls for two MPTs. The second is intended
heat transfer, including graybody radiation with view factor to be used for secondary waste, but it could also be
computation. used for treating munitions bodies in an emergency.
Finding. The MTU could be substituted for the MPT
comParisoN oF The meTal ParTs TreaTer aNd
at BGCAPP; however, it would be necessary to do the
mUNiTioNs TreaTmeNT UNiT For BGcaPP
following:
The committee reviewed the applicability of the MTU
• se supplemental decontamination units and auto-
as an alternate method for decontaminating munitions bodies U
and secondary waste at BGCAPP. As noted above, the MTU claves to treat secondary waste,
• ind another means of treating the detonators in the
is currently planned for installation at PCAPP for the thermal F
decontamination of 155-mm and 105-mm projectiles and 4.2- M417 rocket fuzes,
• odify the MTU design to accommodate 8-in.
in. mortars that have been drained of mustard agent and passed M
through a high-pressure wash. Table S-1 compares various projectiles,
• odify the footprint of the building to accommodate
operating requirements and features of the MPT and the MTU M
and identifies changes that would be required for the MTU to be the units, and
• Modify the existing permits.
used at BGCAPP. The same table appears in Chapter 5, which
gives additional supporting and clarifying information.
Finding. For BGCAPP, the TRRP testing did not address a
method to thermally treat the fuzes and a limited number of
GeNeral FiNdiNGs aNd recommeNdaTioNs
igniters from contaminated propellant that are not decom-
Finding. The full-scale MPT as currently designed for posed in the energetics batch hydrolyzers.
BGCAPP can decontaminate projectile bodies and second-
Recommendation 6-1. The BPBGT needs to develop a
ary and closure waste, and it will be able to achieve its target
throughput rates provided that the BPBGT is able to resolve method to collect and pop the igniters and fuzes that will not
the following issues: adversely affect the operation of the MPT.
• uccessful implementation of new designs for door Recommendation 6-2. To reduce the technical risks in treat-
S
closure and seals, for roller bearings on conveyors, ing secondary waste in the MPT, the BPBGT should continue
and for the superheated steam header; to strive to send secondary waste off-site whenever possible
and minimize the use of halogenated materials.
OCR for page 1
SuMMaRY
Recommendation 6-3. To reduce the load on the off-gas still required. These changes and improvements may require
several iterations before satisfactory results are achieved.
treatment system, the BPBGT should consider obtaining
permits that allow the use of the Airborne Exposure Limit
Recommendation 6-4. A test plan should be prepared for all
Guidelines to operate the MPT at lower temperatures for the
design changes identified for the MPT but not verified in the
thermal treatment of secondary waste whenever possible.
TRRP tests. This test plan should be conducted at the fabrica-
Finding. TRRP testing demonstrated the validity of using tion facility and should include time for the repeated trials
needed to arrive at acceptable performance for the overall
an MPT for thermal decontamination. It also identified
full-scale MPT. A similar test plan should be prepared for
many changes and design improvements that will be neces-
testing the integrated full-scale off-gas treatment system for
sary to achieve an acceptable throughput rate and control
the MPT at BGCAPP. This test plan should include the test-
maintenance and operating costs. Further testing with varied
ing of a full range of secondary, energetics batch hydrolyzer,
secondary waste materials including halogenated waste is
and closure waste at the full-scale MPT design rates.
TABLE S-1 Comparison of the Metal Parts Treater and the Munitions Treatment Unit
Characteristic MPT at BGCAPP MTU at PCAPP Changes for MTU Use at BGCAPP
Status of testing Prototype (~3/4 scale) Full-scale unit completed Full testing would be required, using
demonstrated on surrogate acceptance tests at the the energetic dregs and agent or
munitions and waste streams. manufacturer’s facility with appropriate surrogate material.
Two full-size MPTs will be built surrogate munitions. Only small design changes from the
and tested at the manufacturer’s PCAPP MTU are required. Using the
facility. MTU would save extensive testing
of the MPT with secondary waste.
Treatment of secondary waste in the
SDUa and autoclaves has already been
performed at the other sites.
Feed streams
4.2-inch mortars and base plates None 97,106 (HD) Applies only to PCAPP, no mortar
rounds at BGCAPP.
105-mm projectiles None 383,418 (HD) Not applicable to BGCAPP.
155-mm projectiles 15,492 (H) 299,534 (HD) A new permit will be needed to use
12,816 (VX) the MTU at BGCAPP.
8-inch projectiles 3,977 (GB) None Muffle height must be increased for
use at BGCAPP. The MTU currently
has internal height of 9.75 in. and
width of 30 in.
M55 rockets; undissolved 51,716 (GB) None Squibs and fuzes must be thermally
fragments, including 17,757 (VX) decomposed (must be popped). Some
undissolved squibs and fuzes Method for treating squibs and fragments are combustible and may
from hydrolysis of rocket fuzes in the MPT is to be tested. require inert gas and special baskets if
warhead and rocket motor treated in the MTU or, alternatively,
segments in EBHsb they may be treated in the SDU or
autoclave if WCLc guidelines for off-
site disposal are used.
Secondary waste Thermal treatment in MPT using Treatment in SDU or autoclaves. SDU and autoclave use based on
approach used at ABCDF.d Use
special carrying trays.
at BGCAPP may require special
permitting and higher temperatures
for GB- and VX-contaminated waste.
Only limited testing on various waste
types has been performed in the MPT.
Closure waste Thermal treatment in MPT. Treatment in second SDU. See comments for secondary waste.
Agents destroyed
Mustard Yes Yes continues
OCR for page 1
ReView aNd aSSeSSMeNT OF deVelOPMeNTal iSSueS CONCeRNiNg The MeTal PaRTS TReaTeR deSigN
TABLE S-1 Continued
Characteristic MPT at BGCAPP MTU at PCAPP Changes for MTU Use at BGCAPP
GB and VX Yes None SDU and autoclave would be required
with the MTU for GB- and VX-
contaminated waste streams. This
method of decontamination may
require higher treatment temperatures
to achieve acceptable treatment times
to meet WCL guidelines for off-site
disposal.
Number of units 2 MPTs with one for projectile 2 MTUs with only one ordinarily BGCAPP might require only 1 MTU
processing and one for waste required to meet PCAPP because the number of projectiles is
streams and as a backup spare. processing rates. an order of magnitude less than at
PCAPP; MTU availability expected to
be higher than that of the MPT.
~70 ft long × 40 ft wide × 20 ft ~100 ft long × 30 ft wide × 20 ft
MDBe footprint MTU would require changes
high high in BGCAPP MDB layout to
accommodate longer processing
Total direct footprint for 2 MPTs Total direct footprint for 2 MTUs length and SDU and autoclave units
plus 50 percent of MPT/washout is 5,100 square feet plus 216 and to provide for collection bins for
support room plus MPT cooling square feet for collection bin receiving treated metal parts from
room is 4,640 square feet. enclosures. MTU discharge chute.
Post-treatment agent clearance In exit air lock before leaving level In treated munition collection bin MTU use at BGCAPP would require
A area. in Level D area. permit change for use of current MTU
discharge configuration.
Atmosphere in unit Nitrogen in air locks and Air flowing from both ends of Change in Kentucky permit would be
superheated steam in main muffle to off-gas duct exit from required for use of MTU and SDU or
chamber. muffle system. autoclave.
Off-gas treatment system Flame arrestor, cyclone, bulk Flame arrestor, filter media, bulk Same components, with different gas
oxidizer, venturi scrubber, and oxidizer, venturi scrubber, and flow rates and sizes.
reheater. reheater.
Method of heating 2 induction coils at 450 kW each Resistance heaters at 600 kW None
plus 75 kW resistance heating for
steam superheater.
Method of operation Batch Continuous Would have to change from a batch
stream to a continuous stream.
Char and tar buildup Expected, but the design allows for Secondary waste not processed in Secondary waste not processed in
from secondary waste addressing tar and char buildup. MTU. MTU.
treatment
Method of control of Doors and seals on air locks Curtains on munitions cold feed Curtains on munitions cold feed end
atmosphere in main attached to main chamber. end and cooling section exit of and cooling section exit of muffle.
treatment unit muffle.
Overall availability 83 percent estimated using spare 91 percent estimated for single Both estimates based on using both
(percent of time the MPT. MTU; no estimate given with treatment units.
system will be operating) spare MTU.
Munitions throughput rates
4.2-inch mortars None for BGCAPP ~60/hr
105-mm projectiles None for BGCAPP ~60/hr
155-mm projectiles ~40/hr ~40/hr ~40/hr
8-inch projectiles ~15/hr None MTU should be capable of
modification to achieve BGCAPP 8-
inch projectile processing rates.
aSDU,supplemental decontamination unit.
bEBH,energetics batch hydrolyzer.
cWCL, waste control limit.
dABCDF, Aberdeen Chemical Agent Disposal Facility.
eMDB, munitions demilitarization building.
SOURCE: Adapted from BPBGT, 2007c.