From page 40...
... The Tier 1 -- Analytical Delivery Decision Approach (Tier 1 approach) provides airports with a structured approach to choosing the most appropriate project delivery method for an individual project.
From page 41...
... Adversarial Relationships 19. Construction Claims Other Key: Most appropriate delivery method Appropriate delivery method Least appropriate delivery method X Not Applicable (discontinue evaluation of this method)
From page 42...
... The team 42 A Guidebook for Selecting Airport Capital Project Delivery Methods
From page 43...
... It should include necessary information about the project and address all aspects of the project that may influence project delivery method selection. The intent of the project description is to provide a "snapshot" of the project scope at the time in which the project delivery decision was made.
From page 44...
... It is to the project's benefit if the airport, designers, and constructors are aware of, understand, and are in agreement with these project goals. For example, if a goal to accelerate the start of project revenue is ranked first and a goal of completing the project on budget is ranked third, the ranking of these goals provides the team 44 A Guidebook for Selecting Airport Capital Project Delivery Methods
From page 45...
... Step 3. Review Go/No-Go Decision Points Among the pertinent issues that affect the project delivery decision, there are certain issues that render one or more delivery methods inappropriate.
From page 46...
... Airports frequently give schedule first priority among competing project goals. Airports most fre46 A Guidebook for Selecting Airport Capital Project Delivery Methods Figure 4-2.
From page 47...
... While some states have fully authorized airports to use CMR and DB, there are still some states that prohibit the use of one or all alternative methods. In the spectrum between states that allow full use of alternative methods and those that prohibit them entirely, there are some states that allow alternative project delivery methods with certain conditions (e.g., requiring extra approvals, putting dollar value limits on the volume of DB or CMR contracts, or putting limits on the number of projects using an alternative delivery method each year)
From page 48...
... Review the advantages and disadvantages associated with each delivery method and analyze their implications. In the Issue Advantages/Disadvantages Summary Table, rate the appropriateness of each project delivery method using the following system: ● – Most appropriate delivery method – Appropriate delivery method  – Least appropriate delivery method X – Not applicable (discontinue evaluation of this method)
From page 49...
... Issue Statements Advantage Disadvantage CMR has been shown to work on projects of all sizes and levels of complexity, but the research case studies found that airports tend to select CMR on larger and more complex projects. On projects of large size and complexity, CMR can use multiple bid packages to optimize responses from proposers, but this approach results in more complexity in management.
From page 50...
... Issue Statements Advantage Disadvantage DBB is the base case and will take the longest of the three delivery methods. If an airport is willing to take on coordination responsibility, DBB projects can be awarded to multiple prime contractors to speed the process.
From page 51...
... Issue Statements Advantage Disadvantage Research on project delivery methods suggests that DBB is likely to yield the highest schedule growth due to change orders There is a lack of opportunity to compress a project schedule if problems occur due to the linear nature of DBB. Studies have shown that, on average, DBB has more schedule growth than CMR and DB.
From page 52...
... DB procurement methods do not significantly affect schedule growth control. Issue DBB CMR DB 3.
From page 53...
... Construction Manager at Risk (CMR) Issue Statements Advantage Disadvantag e CMR can be used in conjunction with a GMP pricing structure, which can be useful in negotiating and controlling costs.
From page 54...
... minimize project cost overruns. Advantages/Disadvantages Form -- Cost Control 54 A Guidebook for Selecting Airport Capital Project Delivery Methods Table 4-7.
From page 55...
... Cost Control Key: Most appropriate delivery method Appropriate delivery method Least appropriate delivery method X Not applicable (discontinue evaluation of this method) Comments ____________________________________________________ ____________________________________________________________ ____________________________________________________________ ____________________________________________________________ ____________________________________________________________ Issue 6: Risk Management/Allocation This issue concerns methods for coping with the uncertainties that are inherent in each project delivery method.
From page 56...
... Construction Manager at Risk (CMR) Issue Statements Advantage Disadvantage Construction manager understands and participates in risk allocation and the management process during design.
From page 57...
... Design-Bid-Build (DBB) Issue Statements Advantage Disadvantage Issue DBB CMR DB 7.
From page 58...
... Advantages/Disadvantages Form -- Maintainability 58 A Guidebook for Selecting Airport Capital Project Delivery Methods Design-Bid-Build (DBB) Issue Statements Advantage Disadvantage The opportunity to view completed plans before award allows airports to review maintenance issues in designs.
From page 59...
... Maintainability advantages/ disadvantages summary. Issue DBB CMR DB 8.
From page 60...
... Issue DBB CMR DB 9. Airport Experience/Staff Capability Key: Most appropriate delivery method Appropriate delivery method Least appropriate delivery method X Not applicable (discontinue evaluation of this method)
From page 61...
... Advantages/Disadvantages Form -- Airport Control of Project Tier 1 -- Analytical Delivery Decision Approach 61 Design-Bid-Build (DBB) Issue Statements Advantage Disadvantage The use of prescriptive specifications and complete designs at the time of award provides airports with the most control over the project.
From page 62...
... This issue concerns the multiple effects of security requirements on airport projects and how each project delivery method is impacted by and impacts security requirements. Advantages/Disadvantages Form -- Security 62 A Guidebook for Selecting Airport Capital Project Delivery Methods Table 4-13.
From page 63...
... Construction Manager at Risk (CMR) Issue Statements Advantage Disadvantage Additional CMR experience in design can help minimize impacts on operation and passenger flow.
From page 64...
... Construction Manager at Risk (CMR) Issue Statements Advantage Disadvantage The construction experience of the construction manager can help facilitate stakeholder input.
From page 65...
... Please specify procurement system: (____________________________________) Issue Statements Advantage Disadvantage The owner can require the DB contractor to include a public information and outreach program to facilitate communities' inputs.
From page 66...
... Advantages/Disadvantages Form -- DBE/Small Business Impacts 66 A Guidebook for Selecting Airport Capital Project Delivery Methods Construction Manager at Risk (CMR) Issue Statements Advantage Disadvantage QBS factors can be applied to select only the most highly qualified construction managers.
From page 67...
... Issue Statements Advantage Disadvantage Airports can include DBE requirements in the procurement selection factors for design and construction requirements. Owners can set DBE requirements, but because all subcontractors are not known at the time of award, there is a risk that design-builders may not achieve the DBE goals they specify in their proposals.
From page 68...
... Issue DBB CMR DB 16. Legal and Statutory Constraints Key: Most appropriate delivery method Appropriate delivery method Least appropriate delivery method X Not applicable (discontinue evaluation of this method)
From page 69...
... Issue Statements Advantage Disadvantage Airports can work with designers to incorporate sustainable designs into complete designs through prescriptive specifications. Airports can assume liability when prescribing construction methods.
From page 70...
... Issue Statements Advantage Disadvantage Inclusion of the construction manager in the design process can align team members and lessen adversarial relationships. Negotiation of GMP can create an adversarial situation if the process is not well understood and well managed.
From page 71...
... Issue Statements Advantage Disadvantage Having the constructor on the team early during design can lessen the likelihood of disputes and claims regarding design. Since design and construction contracts are separate, the potential for disputes and claims regarding design still exist.
From page 72...
... Please specify procurement system: (____________________________________) Issue Statements Advantage Disadvantage The single source for design and construction eliminates claims for design errors or omissions from the airport's perspective.
From page 73...
... Construction Claims Other Key: Most appropriate delivery method Appropriate delivery method Least appropriate delivery method X Not Applicable (discontinue evaluation of this method) Project Delivery Advantages and Disadvantages Summary ___________________________________________________________ ___________________________________________________________ ___________________________________________________________ ___________________________________________________________ ___________________________________________________________
From page 74...
... If, at the end of this stage, a dominant choice has not emerged, the airport should document the results and move to the Tier 2 approach for a more detailed analysis of the remaining delivery methods. 74 A Guidebook for Selecting Airport Capital Project Delivery Methods