From page 75...
... Only those project delivery methods that are feasible and have the best potential for successful application will pass through the Tier 1 filtering process. The filtering process involves examination of go/no-go issues and consideration of 19 pertinent issues involved in the project delivery decision.
From page 76...
... The Tier 1 report will provide a project description, project goals, delivery methods considered, advantages and disadvantages, delivery method decision, and any relevant appendices. The Tier 2 documentation will add the weighted-decision matrix to the Tier 1 documentation to sup76 A Guidebook for Selecting Airport Capital Project Delivery Methods Figure 5-1.
From page 77...
... that typically drive the project delivery decision. The first step in the Tier 2 approach requires airports to combine the project goals and pertinent issues into a set of selection factors for use in the weighted-decision matrix.
From page 78...
... 78 A Guidebook for Selecting Airport Capital Project Delivery Methods
From page 79...
... involve combining the weighted rankings with a scoring of the project delivery methods to arrive at a final selection of the most appropriate delivery method. Delivery Selection for the Example Project -- Step 2.
From page 80...
... However, a larger or smaller number of delivery methods can be analyzed, depending upon the results of Tier 1. For example, two types of DB delivery methods with various procurement 80 A Guidebook for Selecting Airport Capital Project Delivery Methods Table 5-3.
From page 81...
... Table 5-4 shows how an airport might score the project delivery methods for the example project. Note that only the CMR and DB project delivery methods made it through the Tier 1 filter for further consideration in Tier 2.
From page 82...
... It should also contain the weighted matrix of Tier 2 and a detailed documentation of the reasoning that was used to assign each criterion weight and project delivery score. A Project Delivery Decision Report outline is offered below: • Executive Summary • Project Description • Project Goals • Delivery Methods Considered • Selection Factors • Weight Selection Factors • Score Project Delivery Methods • Delivery Method Decision • Appendices 82 A Guidebook for Selecting Airport Capital Project Delivery Methods
From page 83...
... At the end of Step 4, there should be a single, clear, and logical choice for a project delivery method, and this choice can be documented in the Project Delivery Decision Report. Tier 2 -- Weighted-Matrix Delivery Decision Approach 83