... Figure 4.2 illustrates how the risk management process focus changes throughout the phases. In the planning phase, the process focuses on risk identification with some initial assessment and planning activities.
From page 41...
... Chapter 5 – Guide to the Planning Phase Chapter 6 – Guide to the Programming Phase Chapter 7 – Guide to the Design Phase Risk Management ProcessAllocate Monitor and Control Identify Assess/ Analyze Mitigate and Plan Level of Complexity • Minor • Moderately Complex • Major Appendix A Chapter 5 – Guide to the Planning Phase Risk Management ProcessAllocate Monitor and Control Monitor and Control Identify Assess/ Analyze Mitigate and Plan Chapter 6 –Guide to the Programming Phase Risk Management ProcessAllocate Identify Assess/ Analyze Assess/ Analyze Mitigate and Plan Mitigate and Plan Chapter 7 – Guide to the Design Phase Risk Management Process Allocate Monitor and Control Identify Figure 4.2. Risk management focus within the project development phases.
From page 42...
... I2.2 Not Used I2.3 Risk Checklists The use of a historical list of project risks from experience or specific past projects that is used to aid in the risk identification process. I2.4 Assumption Analysis The process of reviewing all assumptions for uncertainty that could generate risks.
From page 43...
... R3.5 Estimate Ranges – Monte Carlo Analysis A risk analysis modeling method that uses repeated trials computing probabilistic outcomes of various risk events or uncertainties. The technique is used for both cost and schedule.