Chapter Two - New Airport Terminal Facilities - Where Activation Fits in
Pages 6-7

The Chapter Skim interface presents what we've algorithmically identified as the most significant single chunk of text within every page in the chapter.
Select key terms on the right to highlight them within pages of the chapter.


From page 6...
... One way these problems can be mitigated is by keeping the airport operations team involved throughout the delivery of the project. This can be achieved by completing designs before bidding, assigning airport operations staff to the project delivery team, establishing a robust activation program, and/or delaying procurement decisions until the last responsible moment.
From page 7...
... • Concurrent with the preparation of plans of operation, preparing for trials, developing recruiting and training programs, etc., the airport terminal facility activation team reviews designs, proposals (bids) , contractor submissions, and equipment submissions to confirm that 8 they reflect operational requirements and advises the AEC team of any issues.


This material may be derived from roughly machine-read images, and so is provided only to facilitate research.
More information on Chapter Skim is available.