From page 73...
... Neither operators nor contractors can really be blamed for this situation. There have been no carefully developed standards of performance for pneumatic systems in grain elevators.
From page 74...
... Contractor shall apply to the committee by letter 30 days before a quarterly meeting. Application shall include completion of a document developed for the purpose and generally resembling the Contractor's Qualification Statement of the American Institute of Architects (see Appendix B)
From page 75...
... The competent elevator operator makes sure that his equipment is performing according to design and that it will continue to perform within acceptable tolerances. Besides minimizing hazard, insistence on quality minimizes costs in the long run.
From page 76...
... No visible dust emission from enclosed equipment operating at design capacity, except where structural or mechanical conditions make such performance impossible. Exceptions should be identified in the specifications.
From page 77...
... 3. The agreement should stipulate adherence to the specified design standards, especially those for inlet and transport velocities, hoods, volume flows, transition fittings, and air-to-cloth ratios.
From page 78...
... TABLE 7-1 Sample Check List for Acceptance Test Description of Item to be Checked Design Value Actual Value at 45 Days 1. System airflow (cfm)