... APPENDIX D Naval Facilities Engineering Command Guide Specification 01781
From page 47...
... 1.2.3.1 1.2.3.2 1.2.3.3 1.2.3.4 1.2.3.5 1.2.3.6 Corrective Maintenance Work-Hours 1.2.4 Appendices 1.2.4.1 1.2.4.2 1.2.4.3 1.2.4.4 1.2.4.5 Operating Instructions Safety Precautions Operator Prestart Startup, Shutdown, and Postshutdown Procedures Normal Operations Emergency Operations Operator Service Requirements Environmental Conditions Troubleshooting Guides and Diagnostic Techniques Wiring Diagrams and Control Diagrams Maintenance and Repair Procedures Removal and Replacement Instructions Snare Parts and Supply Lists Parts Identification Warranty Information Personnel Training Requirements Testing Equipment and Special Tool Information Contractor Information 1.3 SCHEDULE OF OPERATION AND MAINTENANCE DATA PACKAGES 1.3.1 Data Package 1 1.3.2 Data Package 2 1.3.3 Data Package 3 1.3.4 Data Package 4 1.3.5 Data Package 5 SECTION 01781 Page 1 47
From page 48...
... 48 APPENDIX D PART 2 PRODUCTS PART 3 ExEcurIoN End of Section Table of Contents SECTION 01781 Page 2
From page 49...
... * DEPARTMENT OF THE NAVY NAVAL FACILITIES ENGINEERING COMMAND GUIDE SPECIFICATION Superseding NFGS-01781B (09/96)
From page 50...
... Refer to paragraph titled "Schedule of Operation and Maintenance Data Packages. n If the product is a ~package" system such as diesel electric generator, the supplier or manufacturer can also provide a manual or data that covers a complete system of interrelated components, including interconnecting wiring diagrams, narrative system control sequences, SECTION 01781 Page 4
From page 51...
... The technical sections should include a paragraph titled "SD-19, Operation and Maintenance Manuals," stating: "Submit Operation and Maintenance Data in accordance with Section 01781, "Operations and Maintenance Data," Data Package Al]
From page 52...
... 1.1.3 Package Content Data package content shall be as shown in the paragraph titled "Schedule of Operation and Maintenance Data Packages." For each product, system, or component piece of equipment requiring submission of O&M Data, submit the Data Package specified in the individual technical section. 1.1.4 Delivery Submit O&M Data Manuals to the Contracting Officer for review and acceptance; submit data specified for a given item within 30 calendar days after the item is delivered to the contract site.
From page 53...
... 1.2.1.3 Startup, Shutdown, and Postshutdown Procedures Provide narrative description for each operating procedure including control sequence for each. 1.2.1 4 Normal Operations Provide narrative description of normal operating procedures.
From page 54...
... _.2.2.2 Preventive Maintenance Plan and Schedule Include manufacturer's schedule for routine preventive maintenance, inspections, tests and adjustments required to ensure proper and economical operation and to minimize corrective maintenance and repair. Provide manufacturer's projection of preventive maintenance work-hours on a daily, weekly, monthly, and annual basis including craft requirements by type of craft.
From page 55...
... 1.2.4.4 Testing Equipment and Special Tool Information Include information on test equipment required to perform specified tests and on special tools needed for the operation, maintenance, and repair of components. 1.2.4.5 Contractor Information Provide a list that includes the name, address, and telephone number of the General Contractor and each subcontractor installing the product or equipment.
From page 56...
... Normal operations c. Environmental conditions d.
From page 57...
... Testing equipment and special tool information Contractor information 1.3.4 Data Package 4 a Safety precautions b. Operator prestart c.
From page 58...
... Environmental conditions h. Lubrication data J ~ Preventive maintenance plan and schedule Troubleshooting guides and diagnostic techniques Wiring diagrams and control diagrams 1.
From page 59...
... APPENDIX D Not used. PART 3 EXECUTION Not used.